Well were about 2weeks out from completion of the home not including outside landscape, pool and some minor details.

Over the last 3 weeks it has been a push of booking 2 and 3 subs at a time with paint, wood trim and electrical along with plumbing. All the finishing touches are about done with the exception of carpet and stained concrete glazing which will be next week.

The pool is also moving along, All rock and tile is completed, Pumps and electrical are done and the concrete salt rock finish deck is currently being formed this week.

I have updated a single gallery of pictures as of Dec 2nd 2008. The home is dusty and still messy but it will be all cleaned by weeks end.